Environment & Forest Department

CENTRAL COALFIELDS LIMITED

DAMODAR BUILDING, DARBHANGA HOUSE,

RANCHI -834029 (0651-2365455); email : forestcclhq@gmail.com ; envccl@gmail.com

ProjectWise Report of CCL
Bokaro & Kargali Area
Khasmahal OC 26.94 ha
Land Details
i Total Forest Land in Ha. 26.94
ii Notified Forest Land in ha 26.94
iii GMK(JJ) in ha 0.00
iv Period of Diversion The period of diversion under this approval shall be twenty (20) years
subject to possession of valid lease by User Agency under the MMDR
Deptt. File No. MoeF File No. Stage-I Stage-II Comp. St-I Comp. St-II Env Clearance
1040 8-37/2003-FC 21-04-2010 06-06-2013 Compliance uploaded J-11015/217/2007-IA.IIM dtd. 2.8.10
Land Details
Movement of Files
FRA, NOC & Site Handover
Staus of Project in Detail
Status As on DateFRA DetailStaus of Project in Details
Rs. 2,38,69,380 paid as NPV on 24.3.17• SDO, Bermowas requested on 11.05.2010 and 30.07.2010 to expedite the clearance under ST & OTFD (Recognition of Forest Rights) Act 2006. • DC, Bokarowas requested for the same on 15.12.2010 & 09.03.2011. DC, Bokaro convened a meeting on 15.03.11 to expedite the clearance under ST & OTFD (Recognition of Forest Rights) Act 2006 • Meeting with Chief Secretary, Govt of Jharkhand along with all DCs held on 15.04.2011 and 29.07.2011 to take expeditious action for clearance under ST&OTFD(Recognition of Forest Rights) Act 2006. • Area has submitted the Revenue Plan along with land schedule to DC, Bokaro on 06.05.2011. • Gram sabha of Bermo village held on 18.04.2011 & 09.05.2011. BDO Bermo gave time till 30.06.11 to finalise claims if any. • Meeting with DC, Bokaro held on 07.07.2011 at the office of SDO, Tenughat. He was apprised with details of Gram Sabha and he was requested to expedite for clearance under ST&OTFD(Recognition of Forest Rights) Act 2006. • Meeting with DC, Bokaro held on 31.10.11 to expediteclearance under FRA. • SDO, Bermo forwarded the proposal to DC, Bokaro on 22.03.2012 for issuance of the said certificate. • Certificate under ST& OTFD (Recognition of Forest Rights) Act 2006 has been issued by DC, Bokaro on 18.05.2012 and sent to Addl. Chief Secretary (Forest), Govt. of Jharkhand on 24.05.2012. • Point wise Compliance of Stage I conditions has been submitted to DFO, Bokaro on 04.09.2010 along with payment of NPV & CA. • Clearance under FRA submitted to DFO, Bokaro in June’ 2012.  
Payment Status
*
Plantation Details*
Chronology
File Movement Date Remarks
FRA / NOC Chronology
File Movement Date Remarks
Application under FRA 15.12.2010 For Bermo Village (26.94 Ha) to DC by letter no. 2770 dt 15.12.2010
FRA issued 18.05.2012