ProjectWise Report of CCL
Bokaro & Kargali Area
Karo Coal Dispatch Conveyor
Land Details
Movement of Files
FRA, NOC & Site Handover
NOC Appl Dt.NOC issue Dt.Village name for NOCFRA Appl Dt.FRA issue Dt. Village Name for FRASite Hand OverDt. of Compliance of Site HandoverDate of DGPS SurveyRef. Work Order of DGPSDate of CA Land Identification Tree enumuration detailPillar Demarcation Detail
30-10-1514-09-16 30-10-1529-09-16   Aug-16 (Forest), 1-9 to 2-9-16 (CA)GM(P&P)/Work order/Karo/2016/933-35 dtd 22-09-16, CGM(P&P)/P&P/2016/866-67 dtd. 13-9-16NA1641In Progress
Staus of Project in Detail
Status As on DateFRA DetailStaus of Project in Details
GOJ forwarded the proposal to MoEFCC, New Delhi on 26.05.2017. MoEFCC asked the GOJ whether this application forms the integral part of Karo (226.67 Ha). FAC held on 26.10.2018. Minutes issued. Compliance to additional information sought by MoEF&CC on 06.12.2018 submitted to DFO Bokaro on 21.01.2019. Proposal forwarded by CF to RCCF on 23.04.2019.Nodal Officer raised queries to RCCF Bokaro on 10.05.19 regarding KML of entire Belt conveyor. Compliance submitted on 03.07.2019. RCCF Bokaro recommended the proposal to ed Nodal on 16.07.19. ED Nodal raised queries on 13.09.19. DGPS plan and KML submitted to DFO Bokaro on 6.10.2020. DFO Bokaro asked Assistant Conservator of Forest on 07.12.2020 for site inspection of the site. Assistant conservator of forest carried out site inspection on 21.01.2021. • Gram Sabha held successfully on 15.02.2016. • 11 no. of claims have been received in GramSabha. • NOC issued on 14.09.2016 • FRA issued on 29.09.16 • Online application on 30.10.2015 • NOC issued on 14.09.2016 • The DGPS map of CA land submitted to DFO, Bokaro on 19.09.2016. • FRA issued on 29.09.16 • PCCF forwarded the proposal to state govt on 18.11.2016 • Querry raised by Dy Secy GOJ regarding FRA and NOC on 1.12.16. • Reply submitted to DFO Bokaro on 8.12.16. • The proposal has been sent to MoEF on 23.03.2017 • DCF RO, MoEFCC Ranchi has advised that the proposal for 7.5 Ha of coal dispatch conveyor is a part of Karo OCP (226.67 Ha)therefore the instant proposal will be considered by the office after final decisionon the main proposal by the Ministry. However the instant proposal may be submitted to the Ministry, Head Office directly to enable them to have comprehensive view on the matter. • GOJ forwarded the proposal to MoEFCC, New Delhi on 26.05.2017. FAC awaited. MoEFCC has asked the GOJ whether this application forms the integral part of Karo (226.67 Ha). FAC held on 26.10.2018. Minutes issued. Compliance to additional information sought by MoEF&CC on 06.12.2018 submitted to DFO Bokaro on 21.01.2019. Proposal forwarded by CF to RCCF on 23.04.2019.Nodal Officer raised queries to RCCF Bokaro on 10.05.19 regarding KML of entire Belt conveyor. Compliance submitted on 03.07.2019. RCCF Bokaro recommended the proposal to ed Nodal on 16.07.19. ED Nodal raised queries on 13.09.19.
Payment Status
*
Plantation Details*
Chronology
File Movement Date Remarks
Online Application 30.10.2015
Reply to DFO 10.11.15 no JJ & Land schedule attached
rev plan submitted to DFO 19.11.15
DFO to PO Karo 30.12.2015 Componentwise breakup sought
Reply to DFO 29.1.16 Compliance to DFO letter 2644 dtd. 30-12-15
DFO to PO karo 10.03.16 Reminder to eariler letter
DFO to PO karo 11.06.16 Reminder to eariler letter
DFO to GM(B&K) 26.08.16 DGPS & KML file for CA requested
DGPS map of CA land 16.09.2016 this is in continuation to DGM 241 dtd. 5-9-16- DGPS map of CA land submitted to DFO, Bokaro
PCCF to GOJ 18.11.2016
Query raised by Dy Secy GOJ & DFO 01.12.2016(GOJ)
8-12-16(DFO)
Regarding FRA and NOC
Reply submitted to DFO Bokaro 8.12.2016 Reply to DFO & GOJ - 6 points - study of alt site, Land acquired under CBA, NOC & FRA
GoJ to MoEFCC 24.03.2017
FRA / NOC Chronology
File Movement Date Remarks
Gram Sabha 15.02.2016 Held successfully- 11 no. of claims have been received in Gram Sabha
NOC issued 14.09.2016
FRA issued 29.09.2016
.
Payment Details
Payment Type Date Remarks