Environment & Forest Department

CENTRAL COALFIELDS LIMITED

DAMODAR BUILDING, DARBHANGA HOUSE,

RANCHI -834029 (0651-2365455); email : forestcclhq@gmail.com ; envccl@gmail.com

IdName of officeDate of Entry by AreaHelp Required from HQDate of Entry by Forest Deptt, CCLHelp required from AreaIssues Resolved This Month
1ARGADA AREA  28.02.19Submission of compliance to the query raised by DFO RamgarhSubmission of DGPS & KML of CA Land of Argada OCP (233.88 Ha)
2BARKASAYAL AREA  28.02.191) Saunda D Project (16 Ha)- Please arrange for the submission of DGPS of CA land. 2) Urimari OCP (34.64 Ha)- Please arrange forest application for remaining area as submitted in compliance. FRA to be obtained 3) Submit compliance report of forest clearance (Stage I Stage II already accorded) Forwarding of the proposal of Urimari OCP (34.64 Ha) from Nodal Officer to GOJ
3B&K AREA Inspection of RO Ranchi for Konar Washery (68.40Ha), Karo 226.67 Ha may please be arranged28.02.19Konar Washery: 1. Application for 19Ha Landuse plan to be submitted Submission of compliance to the Stage I conditions of karo OCP (226.67 Ha)Compliance of Karo CDC (7.5 Ha) submitted on 21.01.2019
4DHORI AREA  28.02.191)Dhori (E) OCP (25.4 Ha)- Please arrange for the submission of authenticated land schedule along with other details for making online forest application. 2) Kalyani OC- Please arrange for the submission of authenticated land schedule alonngwith other details for making online forest application. 1) Forwarding of the proposal of Sel Dhori OCP (7.45 Ha) from NO to GOJ on 22.02.2019 2)Forwarding of the proposal of Amlo OCP (39.663 Ha) from NO to GOJ on 22.02.2019. 3) Hard copies submitted to DFO Bokaro on 06.092.2019 in respect of tarmi OCP (147.35 Ha)
5HAZARIBAGH AREA Kindly expedite the submission of fresh compliance of stage-I clearance already granted for Kedla OCP 168.5 Ha and Kedla UG 29.19 Ha 28.02.191) Submit compliance report of forest clearance (Stage I and Stage II already accorded) 2) Submit compliance to EDS in respect of Parej to be submitted.. 3) Land schedule for Jharkhand renewal, Jharkhand rest and Tapin south to be submitted. Proposal of 43.52 Ha and 7.10 Ha delinked on MoEF&CC portal on 28.02.2019
6KATHARA AREA  28.02.191) Submit compliance report of forest clearance (Stage I Stage II already accorded) Govindpur Ph II 
7KUJU AREA Segregation of CA land for Kuju, Pundi and Topa may please be arranged for making DGPS plan28.02.191) Kuju OCP (92.59 Ha)- provide authenticated land schedule and other relevant documents for making revised forest application as per fresh PR 2) Pundi Exp. OCP(595.53 Ha)- Revised forest application to be submitted 3) Pindra - Submit documents for making application for land use change. 4) Please follow up for the site handover of Pundi, Karma OCPProposal of kuju Patch (5 Ha) withdrawn
8M&A AREA  28.02.191) Amrapali OCP(432.59 Ha)- Please arrange for the early compliance of queries raised by DFO Chatra. 2)Magadh OCP (659.05 Ha)- Please arrange for the submission of hard copies to the office of DFO. 3) FRA of remaining forest area falling under Latehar district is to be obtained. 4)NOC of GMK JJ falling under Latehar district is to be obtained. Masilong to Chatra Khelari Road (10.72 Ha) & Honhe to Saradhu Road (13.70 Ha) forwarded from DFO Chatra to CF Chatra on 16.02.2019
9NK AREA  28.02.191) Payment of NPV for Dakra to be initiated. 2) Compliance to the queries raised in respect of Churi Benti (281.17 Ha) 3) Preparation of DGPS & KML of CA land for KDH (126.72 Ha) is URGENTLY required. 4) Site inspection of Regional office of MoEFCC to be arranged for Purnadih & KDH. Compliance to the query raised by ROMoEF&CC for KDH OCP (126.72 Ha) submitted on 20.02.2019
10PIPARWAR AREA  28.02.19 1)Piparwar Railway Siding (29.5 Ha)-A copy of FRA issued has not been submitted to this office 2) Wharf wall of Piparwar Railway siding ( 4.51 Ha)- Kindly arrange for the submission of compliance of queries raised through EDS by Nodal Officer. 3) Submit compliance report of forest clearance (Stage I Stage II already accorded)  
11RAJHARA AREA  28.02.19Land schedule for making application for release of GMJJ land to be submitted. 
12RAJRAPPA AREA  28.02.191) Application for temporary permission to Rajrappa Bridge made. 2) Additional information sought by MoEF&CC in FAC to be submitted.. Compliance to the Additional information sought by MoEF&CC submitted on 15.02.2019
13GM PP  28.02.1912 copies of mine plan required for all new projects for making application for forestry clearance. 
14DT PP     
15CMD SECT     
16CIL NEW DELHI  28.02.19Kindly arrange clearcut proceedures and items to be taken in CBA report preparation in line with CBA guidelines issued by MoEFCC on 1.8.17.  
17CIL KOLKATTA  28.02.19 Report on milestone projects sent Report of major projects sent. Report of Payment status and FC status submitted to GM (PMD) Kolkata
Status of Help Required & Information to Update

Date of Entry :

Enter Help Required from Area :

Enter Issues Resolved This month: